Mersing Shore End Completed With HDD, BMH, PLSE Cable Pulling, and Clearing of Site, All 48 Fiber Cores Are Within Specified Results With OTDR Test
Laying of the PLSE Cable Process and Landing into Mersing
SEAX-1 Segment 1 Mersing PLSE Cable Landing October 10th, 2017 Optic Marine Services’ Cable Installation Barge ‘Cable Orchestra’ ‘Dragon Sledge’ plough share depth calibration Barge cable tank with 7.2 kms Segment 1 Mersing shore end cable Messenger rope with cable end about to enter LCE Cable end entering plough bell mouth Messenger rope overboard commencing […]
Latest Update on the Progress of Our SEAX-1 Submarine Cable Project at Mersing
Completed BMH, Grounding and PLSE work in progress BMH ( Beach Manhole ) : BMH ( Beach Manhole ) Grounding Work : HDD ( Horizontal directional drilling ) Works : ‘ PLGR, and PLSE mobilization : […]